2/3/26 - Assigned by GNY as Construction Experts
2/4/26 - Inspected damage and provided emergency service
2/6/26 - Inspected loss with our architect
2/7/26 - Submitted our repair estimate to GNY
2/13/16 - Presented proposed contract to Association
3/3/26 - Met with Board via Zoom
3/6/26 - Board selected Accurate Reconstruction to perform all repairs
3/12/26 - Introductory meeting with homeowners, via Zoom
3/16/26 - We have submitted all building permits and will now wait for approval
4/10/26 - As soon as the scene is cleared by the investigators we will begin our work. This still may take a several weeks.
Accurate Reconstruction at The Point at Galloping Hill